Pipeline Integrity Assessment and life extension for 2 nos. export pipelines (WHP-E &F)

Activity  Objective of the work is to carry-out fitness for service assessment.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Kuala Lumpur and Abu-Dhabi, U.A.E.

Pipeline route    From      WHP-B  WHP-C  WHP-D  WHP-E  WHP-F

               To          CCP        CCP        CCP        CCP        CCP

Pipeline Integrity Assessment and life extension for 3 nos. export pipelines (WHP-B/C/D)

Activity  Objective of the work is to carry-out fitness for service assessment.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Kuala Lumpur and Abu-Dhabi, U.A.E.

Pipeline route    From      WHP-B  WHP-C  WHP-D  WHP-E  WHP-F

               To          CCP        CCP        CCP        CCP        CCP

Digitalization of Bunduq Drawing (Phase-4)

Activity  Objective of the work is to produce CAD drawings in accordance with the analogue drawings.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Abu-Dhabi, U.A.E.

Period   Phase I: Aug 2013- Nov 2013       Phase II: Nov 2013 – Jan 2014

               Phase III: Jan 2014- April 2014     Phase IV: June 2014 – Aug 2014

 

Digitalization of As-Built Drawing (Phase-3)

Activity  Objective of the work is to produce CAD drawings in accordance with the analogue drawings.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Abu-Dhabi, U.A.E.

Period   Phase I: Aug 2013- Nov 2013       Phase II: Nov 2013 – Jan 2014

               Phase III: Jan 2014- April 2014     Phase IV: June 2014 – Aug 2014

 

Digitalization of As-Built Drawing (Phase-2)

Activity  Objective of the work is to produce CAD drawings in accordance with the analogue drawings.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Abu-Dhabi, U.A.E.

Period   Phase I: Aug 2013- Nov 2013       Phase II: Nov 2013 – Jan 2014

               Phase III: Jan 2014- April 2014     Phase IV: June 2014 – Aug 2014

 

Digitalization of As-Built Drawing (Phase-1)

Activity  Objective of the work is to produce CAD drawings in accordance with the analogue drawings.

Client     Bunduq Company Limited, Abu-Dhabi, UAE.

Place     Abu-Dhabi, U.A.E.

Period   Phase I: Aug 2013- Nov 2013       Phase II: Nov 2013 – Jan 2014

               Phase III: Jan 2014- April 2014     Phase IV: June 2014 – Aug 2014

 

Repair of 4” GRE Pipeline Between WHP-A & CPP

Activity  Engineering study of the subsea GRE pipeline for review of the current and prospective integrity of the line with a view to making recommendations for future continued functionally of the pipeline.

Client     Bunduq Company Limited (BCL), Abu-Dhabi, UAE.

Place     Arabian Gulf Abu-Dhabi, U.A.E.

Period   March 2011 to April 2011.

 